Page 1 of 1
[2.0.69] consumer of 2 power networks won't function until min consumption is met
Posted: Wed Nov 05, 2025 5:18 pm
by AntiElitz
Re: [2.0.69] consumer of 2 power networks won't function until min consumption is met
Posted: Wed Nov 05, 2025 5:28 pm
by boskid
I am considering this bug report to be essentially a duplicate of
105074 - chemical plant has 7kW drain and is within 2 electric networks. During update, first electric network charges chemical plant with equivalent of 6.6kW from solars while not applying drain (because that is a secondary electric network), then the other electric network updates, drain is applied causing buffer to be emptied and there is no energy left for the chemical plant. If electricity would be provided through a primary electric network, then drain that applies first would see no energy to be removed, 6.6kW would be added to the chemical plant buffer and during entity update a chemical plant would be able to use that energy.
Re: [2.0.69] consumer of 2 power networks won't function until min consumption is met
Posted: Wed Nov 05, 2025 5:56 pm
by AntiElitz
Interesting. No fix is fine for me. I can just build the other network first.
Thanks for explaining!