[Klonan] [2.0.23] Science production information GUI shows progress values of next tech on completion

Posted: Tue Dec 10, 2024 2:17 am
by MatroDulce
After completing an infinite technology research, the "Progress" will display the total for the next level, not the completed level. For example, when researching "Health 2" the progress will go from "199 / 200" to "400 / 400". I noticed this on Artillery Shell Damage 5, but reproduced it with Health 2 so I could capture a video.
science_progress_display_bug.mp4
(2.01 MiB) Downloaded 33 times

Re: [Klonan] [2.0.23] Science production information GUI shows progress values of next tech on completion

Posted: Thu Dec 12, 2024 3:54 pm
by Klonan
Thanks for the report,

It is fixed for the next release