[Genhis][2.0.15] Cancelling upgrade does not cancel requests for nonexistent upgrade slots
Posted: Wed Nov 13, 2024 7:35 am
- What did you do?
- Used Alt+U upgrade planner to schedule an upgrade for an assembly 2 to assembly 3.
- Used map view to get ghost speed modules in hand and ctrl+click to schedule module insertion to all slots.
- Used Alt+U upgrade planner to shift+click unschedule assembly machine upgrade.
- Cancelled plans for module slots 1 and 2 manually by opening entity panel and right clicking the modules.
- What happened?
- Plan indicators for module slots 3 and 4 remained.
- What did you expect to happen?
- Module slots 3 and 4 should be automatically cleared as assembly 2 does not support them.
- Does this happen always?
- Yes.